Here is the questions and below that is the answer in the ch
Here is the questions and below that is the answer in the chart. I just need help explaining what actions as a planner I can take since in week 3 of the revised I will be -25? Thanks!
following MRP recor What will happen if the gross requirements in weelk 3 are increased to 150 units? As a planner, what actions can you take? Week 50 125 200 100 i0 Gross Requirements Scheduled Receipts Projected Available 100 Net Requirements Plared Order Receipt 40 Material Requirements Plannins 95 Revial MRP Week Gross Requirements Scheduled Receipts Projected Available 100 Net Requirements Planed Order Receipt Planned Order ReleaseSolution
To handle the situation, the planner can use action notices or rescheduling notices. Rescheduling notice would help to make the necessary changes in the existing MRP plan.
