ASAP Question 1 The section of the project management plan

ASAP

Question 1

The ____ section of the project management plan describes how to monitor project progress and handle changes.

a.

management objectives

b.

project controls

c.

risk management

d.

technical processes

Question 2

One method for selecting projects based on ____ is to determine whether they first meet three important criteria: need, funding, and will.

a.

broad organizational needs

b.

using a weighted scoring model

c.

implementing a balanced scorecard

d.

categorizing information technology projects

Question 3

____ are new requirements imposed by management, government, or some external influence.

a.

Opportunities

b.

Commands

c.

Problems

d.

Directives

Question 4

The majority of time on a project is usually spent on ____, as is most of the project’s budget.

a.

execution

b.

planning

c.

closing

d.

monitoring and controlling

Question 5

There are ____ main processes involved in project integration management.

a.

three

b.

six

c.

ten

d.

fifteen

a.

management objectives

b.

project controls

c.

risk management

d.

technical processes

Solution

b. project controls

a. broad organizational needs

d. Directives

a. execution

b. six

ASAP Question 1 The ____ section of the project management plan describes how to monitor project progress and handle changes. a. management objectives b. projec
ASAP Question 1 The ____ section of the project management plan describes how to monitor project progress and handle changes. a. management objectives b. projec

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site