A test-fix-test reliability growth program conducted growth testing in 100-hr increments with the following results:

Fit a Duane growth curve and estimate the additional time necessary to achieve an MTTF of 50 hrs

Hours of test Number of failures
0-100 23
100-200 15
200-300 9
300-400 5
400-500 2
500-600 2
600-700 1
700-800 1

Solution

A test-fix-test reliability growth program conducted growth testing in 100-hr increments with the following results: Fit a Duane growth curve and estimate the a