The contractor reports a cumulative cost variance CV of 50K

The contractor reports a cumulative cost variance (CV) of $50K and a variance at completion (VAC) of -$20K. What can you conclude from these metrics?

(A) You must know the percent values to draw conclusions.
(B) The contractor is predicting better future cost performance.
(C) You cannot draw conclusions based on this type of comparison.
(D) The contractor is predicting worse future cost performance.

Solution

The correct answer is Option D i.e. The contractor is predicting worse future cost performance.

Because the final variance and estimated variance is no where close to each other that the prediction of the contractor the absolutely vague and baseless.

The contractor reports a cumulative cost variance (CV) of $50K and a variance at completion (VAC) of -$20K. What can you conclude from these metrics? (A) You mu

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site