3 Mubarak 2015 Ex62 modified In the following network try to
3. (Mubarak 2015, Ex.6.2 modified) In the following network, try to develop a minimum duration project schedule while maintaining the maximum daily resource requirements no more than eight laborers per day (30%): Activity Duration (Days) IPA Laborers 4 A, B 4 10 D, E C,F, G C, G H,I
Solution
Minimum duration in only the minimum path of activity.
Draw the activity & event of the above given value.
And find the minimum path of this activity.