Find the expected production of a pusherscraper operation fo
Solution
production of a pusher(komatsu D155) scrapper(16637D-CAT)
efficiency is taken as 50min/hr = 50/60 =0.83 (83%)for no data is given by the company
specificationss of komatsu D155:
cycle time= 4
volume per load = 12.3yd3
specifications of 16 637D-CAT :
cycle time in specification is given that fast cycle times hence use cycle time formula for scrapper to calculate the cycle time tp = 1.44Ll + 0.25where Ll= loading timeof scrapper usally taken as o.85min.
now cycle time = 1.44*0.85 + 0.25 = 1.44min.
volume per load =34 yd3
no.of scrappers is taken as 2
productionof pusher = efficiency min/hr*volume perload /toatl cycle time
= 50*12.3/4 = 153.75 bcy/hr
production rate of scrapper = efficiency min/hr*no.of scrappers *volume perload /toatl cycle time
= 50*2*34/1.44 =2361.11bcy/hr
toatl production rate = 153.75+2361.11 = 2514.86bcy/hr =2537bcy/hr