It took a contractor 1285 hours to manufacture their first u
It took a contractor 1285 hours to manufacture their first unit of an item. If the contractor expects to achieve a 94% unit learning curve, how many hours would be required to manufacture units 52-100?
A) 50,475
 B) 42,851
 C) 41,948
D) 44,398
Can you please show the work. Thank you!
Solution
Answer to the question)
Learnign curve equation is = a* X^b
Where a = 1285
b = log(0.94) / log(2)
b = -0.02687 / 0.301
b = -0.08927
.
We got X1 = 52
X2 = 100
Y = (1285 *(100)^-0.08927) - (1285 * (52)^-0.08927)
Y = 50475