Question2 5 pts If MARR7 which alternative should be selecte

Question2 5 pts If MARR=7%, which alternative should be selected? Year 0 -18,000 7,000 7,000 24,500 9,500 9,500 9,500 2 Alt. B Alt. A Either Alt. A or B

Solution

Both projects can be accepted as IRR of both the projects is greater than MARR and NPV of both Projects is positive.

Hence option “Either Alt. A or B” is correct answer.

Explanation:

Computation of IRR and NPV of both the projects:

Year

Cash Flow

(CA)

Cash Flow (CB)

PV Factor calculation

PV Factor

(F)

PVA (=CA x F)

PVB (=CB x F)

0

($18,000)

($24,500)

1/(1+7%)^0

1

($18,000.00)

($24,500)

1

$7,000

$9,500

1/(1+7%)^1

0.934579439

$6,542.06

$8,879

2

$7,000

$9,500

1/(1+7%)^2

0.873438728

$6,114.07

$8,298

3

$7,000

$9,500

1/(1+7%)^3

0.816297877

$5,714.09

$7,755

IRR

8.12%

7.96%

NPV

$370.21

$431.00

Sum of all PV is NPV and Excel formula for IRR is:

“=IRR(Cell no: Cell no)”

Year

Cash Flow

(CA)

Cash Flow (CB)

PV Factor calculation

PV Factor

(F)

PVA (=CA x F)

PVB (=CB x F)

0

($18,000)

($24,500)

1/(1+7%)^0

1

($18,000.00)

($24,500)

1

$7,000

$9,500

1/(1+7%)^1

0.934579439

$6,542.06

$8,879

2

$7,000

$9,500

1/(1+7%)^2

0.873438728

$6,114.07

$8,298

3

$7,000

$9,500

1/(1+7%)^3

0.816297877

$5,714.09

$7,755

IRR

8.12%

7.96%

NPV

$370.21

$431.00

 Question2 5 pts If MARR=7%, which alternative should be selected? Year 0 -18,000 7,000 7,000 24,500 9,500 9,500 9,500 2 Alt. B Alt. A Either Alt. A or B Soluti
 Question2 5 pts If MARR=7%, which alternative should be selected? Year 0 -18,000 7,000 7,000 24,500 9,500 9,500 9,500 2 Alt. B Alt. A Either Alt. A or B Soluti

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site