Tasya has to provide estimates for activities but no one on
     Tasya has to provide estimates for activities, but no one on the project team has performed them before. The project team is using a schedule from a similar project as the basis for its estimates. What type of estimating is this an example of?  Select one:  Budgetary  Three-point estimate  Parametric  Analogous  The actual cost for a previously budgeted procurement item is five percent more than expected. Where would this extra cost most likely be drawn from?  Select one:  Critical chain reserve  Management reserve  Contingency reserve  Budget allowance  Which one of the following is not an output of any of the processes in the Project Time Management knowledge area?  Select one:  Resource breakdown structure  Project schedule network diagram  Schedule model data  Schedule management plan Work expands to fill the time available refers to which of the following?  Select one:  Monte Carlo Analysis  Parkinson\'s Law  Contingency reserve analysis  Design of experiments 
  
  Solution
Question 2:
D : ANALOGOUS ESTIMATING
Analogous estimating uses a similar past project to estimate the duration or cost of your current project, thus the root of the word: analogy.
Question 3:
C: Contingency reserve
Question 4:
A: Resoruce breadkwong structure
Question 5
B: Parkinson´s Law
This statement was made by Cyril Northcote Parkinson, the famous British historian