Calculating ActivityBased Costing Overhead Rates 1 Calculate

Calculating Activity-Based Costing Overhead Rates

1. Calculate the cost per unit of activity driver for each activity cost category.
Setup $_____
Production scheduling $______
Production engineering $______
Supervision $_______
Machine maintenance $______

2. Calculate the cost of Job 845 using ABC to assign the overhead costs.

$______

3. Calculate the cost of Job 845 using the plantwide overhead rate based on machine hours. (Round your answer to the nearest dollar.)
$_____


A food company had the following activities and costs:

The following additional data were provided for Job 845:

Setup (1,000 setup hours) $118,000
Production scheduling (400 batches) 60,000
Production engineering (60 change orders) 150,000
Supervision (2,000 direct labor hours) 46,000
Machine maintenance (12,000 machine hours) 60,000
Total activity costs $434,000

Solution

1. Calculate the cost per unit of activity driver for each activity cost category.

2. Calculate the cost of Job 845 using ABC to assign the overhead costs.

3. Calculate the cost of Job 845 using the plantwide overhead rate based on machine hours. (Round your answer to the nearest dollar.)

Overhead rate = 434000/12000 = 36.167 per machine hour

Setup (118000/1000) 118 per setup
Production scheduling (60000/400) 150 per batch
Production engineering (150000/60) 2500 per change order
Supervision (46000/2000) 23 per direct labour hour
Machine maintenance (60000/12000) 5 per machine hour