For the attached drawing calulate the total top soil 6 inche
For the attached drawing calulate the total top soil (6 inches) to be stripped from the building AND PARKING/SIDEWALK areaS in BCY take the cut to 5\' outside the construction line?
50\'-0\" 4J\'-0\" 74\'-0 30\'-0\" 20\'-0 20-0 N ELOOR 104 PARKING (5\" COARSE ASPHALT AVING OVER 8\" COMPACTED CRUSHED GRAVEL 15\'-0\" DEWALK HICK CONCHE EEIN WWM. 20-0\" 30\'-0\" 20\'-0 20-0 38-6 38\'-6\" FRONT STREETSolution
Proposed Building area
 with 5\'clearance on each side = 50 x 90 sqft
 A. Total volume of soil (6\") = 50 x 90 x 0.5 = 2250
 Parking Area
 with 5\'clearance on each side = 74 x 89 sqft
 B. Total volume of soil (6\") = 74 x 89 x 0.5 = 3293
 Drive way near front street  
 since already 5\'clearance is considered above the
 remaining area is taken
 (Assuming the front street not disturbed)
 Area to be cleared = 3 x 30 sft
 c. Total volume of soil (6\") = 3 x 30 x 0.5 = 45
 Drive way in the rear side
 with 5\'clearance on each side = 11.5 x 30 sqft
 D. Total volume of soil (6\") = 11.5 x 30 x 0.5 = 172.5
 Sidewalk area with clearance = 38.5 x 20 sqft
 E. Total volume of soil (6\") = 38.5 x 20 x 0.5 = 385
 There is another passage running between building
 and parking which is 15\'x 15
 Out of which we have to take remaining area
 Length = 15 - 4-5-5 = 1
 Width = 15+5+5 = 20
 F.Volume of soil (6\") = 1 x 25 x 0.5 12.5
 TOTAL = A + B+ C+ D+E+F 6158 Cft
 Total soil in BCY = 228.07 cubic yards