The demand for subassembly S is 120 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 2 units of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 2 weeks to make T, 2 weeks to make U, 2 weeks to make V, 2 weeks to make W, 1 week to make X, 2 weeks to make Y, and 2 weeks to make Z. In addition to 120 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in w eek 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used).Solution