The purchasing manager for Alpa Enterprises requested the following data from the accounting department:
 Annual demand = 15,500; Cost of placing an order = £180; Annual inventory holding costs = 20 percent; Unit cost = £753
 
 Assume Alpha’s demand for an item during the lead time is normally distributed with a mean of 5,000 and a standard deviation of 50. What reorder point should be used in order to average no more than one stock out every 20 re-order cycles? If safety stock is 70, how often will a stock out occur during a re-order cycle?
    The purchasing manager for Alpa Enterprises requested the following data from the accounting department:
 Annual demand = 15,500; Cost of placing an order = £180; Annual inventory holding costs = 20 percent; Unit cost = £753
 
 Assume Alpha’s demand for an item during the lead time is normally distributed with a mean of 5,000 and a standard deviation of 50. What reorder point should be used in order to average no more than one stock out every 20 re-order cycles? If safety stock is 70, how often will a stock out occur during a re-order cycle?
   The purchasing manager for Alpa Enterprises requested the following data from the accounting department:
 Annual demand = 15,500; Cost of placing an order = £180; Annual inventory holding costs = 20 percent; Unit cost = £753
 
 Assume Alpha’s demand for an item during the lead time is normally distributed with a mean of 5,000 and a standard deviation of 50. What reorder point should be used in order to average no more than one stock out every 20 re-order cycles? If safety stock is 70, how often will a stock out occur during a re-order cycle?
Given,
 Annual demand = 15500
 Cost of placing an order = 180/-
 Annual inventory holding cost = 20%
 Unit cost = 753/-
 Mean = 5000 units
 Standard deviation = 50 units
 Safety stock = 70 units
 Lets assume the lead time for an order is 10 days and also the number of working days of the enterprise are 300 days per year
 then the average daily sales will be 15500/300 = 52 units per day
 lead time = 10 days
 then the Reorder point will be Average daily sales multiplied by the lead time plus the safety stock = 52*10+70 = 590 units
 Reorder point = Lead time demand + Safety stock
 Safety stock = Service level(Not mentioned in the question) * Standard deviation of lead time
 So 20 reorder cycles = 590 * 20 =11800 units should be used to average no more than one stock of every 20 reorder cycles.