Hi there I was just curious if I did the following right Can
Hi there I was just curious if I did the following right. Can you please help?
Solution
Your answer is correct.
Here is the explanation
Minimum values on Machine 1 and 2 (18,10) for A . Minimum is in machine 2 so assign job A in the last
strike off A and find the minimum values on M1 and M2 are (20,28) of job D. since minimum is in M1 so assign job D first.
strike off D and proceed in the above manner . Minimum value (35,30) of Job C. assign job C prior to A
after strike off C, next minimum values ((40,45) of Job B. assign Job B next to D.
only Job E left, assign after B.
Hence the schdule is DBECA