9. Billy Baroo Company uses a job costing system. The following information was work-in-process account for the month of July, 20X0 found in the Date July 1 July 31 July 31 July 31 July 31 Description Balance Direct labor Direct materials Manufacturing overhead Transfer to Finished Goods Amount- Dr.(Cr.) $10,000 $38,000 $52,000 S30,400 ($75,000) Billy Baroo applies manufacturing overhead to production at a predetermined rate of 80% based on the direct labor cost. Job #23, the only job still in process at the end of July 20X0, has been charged with direct labor of $20,000. Direct material charged to Job #23 was A) $14,400. B) $10,500. $27,000. D) $19,400. ) None of the above.

Solution

9. Answer is D

Working:

10. Answer is C.

  Working:

11. Answer is B

12.Answer is C

Ending balance of work-in-process

13. Answer is A

Beginning Balance 10000
Direct labor 38000
Direct material 52000
Manufacturing overhead 30400
Total cost charged 130400
Less: Transferred to finished goods 75000
Balance of ending work in process 55400
Cost of Job#23 55400
Less: Direct labor for Job#23 20000
Less: Manufacturing overhead Job#23 (80% of $20,000) 16000 36000
Direct material charged for Job#23 19400