 9. Billy Baroo Company uses a job costing system. The following information was work-in-process account for the month of July, 20X0 found in the Date July 1 July 31 July 31 July 31 July 31 Description Balance Direct labor Direct materials Manufacturing overhead Transfer to Finished Goods Amount- Dr.(Cr.) $10,000 $38,000 $52,000 S30,400 ($75,000) Billy Baroo applies manufacturing overhead to production at a predetermined rate of 80% based on the direct labor cost. Job #23, the only job still in process at the end of July 20X0, has been charged with direct labor of $20,000. Direct material charged to Job #23 was A) $14,400. B) $10,500. $27,000. D) $19,400. ) None of the above. Solution
9. Answer is D
Working:
10. Answer is C.
Working:
11. Answer is B
12.Answer is C
Ending balance of work-in-process
13. Answer is A
| Beginning Balance | 10000 | |
| Direct labor | 38000 | |
| Direct material | 52000 | |
| Manufacturing overhead | 30400 | |
| Total cost charged | 130400 | |
| Less: Transferred to finished goods | 75000 | |
| Balance of ending work in process | 55400 | |
| Cost of Job#23 | 55400 | |
| Less: Direct labor for Job#23 | 20000 | |
| Less: Manufacturing overhead Job#23 (80% of $20,000) | 16000 | 36000 | 
| Direct material charged for Job#23 | 19400 | 