Identify the four engineering economy symbols and their values from the following problem statement. Use a question mark with the symbol whose value is to be determined.

Solution

PW ---> Present Worth

PV ----> Present Value

NPV ---> Net Present Value

DCF ---> Discoutted Cash Flow

CC ----> Correlation Coefficient.

1.15. Identify the four engineering economy symbols and their values:

P = $150,000

i = 11%

n = 7 years.

F (?) = $150,000 + interest

F = $150,000 + $115,500 = $265,500.

***

 Identify the four engineering economy symbols and their values from the following problem statement. Use a question mark with the symbol whose value is to be d