3. The anticipated time of completion for a housing project is 4 years. However, this is conditional on having good weather for atleast 3 years continuously. If there is a 50% chance of having good weather in any given year, what is the probability that the housing project will be completed in the anticipated 4-year time?
Solution
Given,
For the successful completion of the project within 4 years , we need three good weather years continously. And that there is 50% chance of having good weather in any given year.
So , There are only two possible ways in which the house can be completed successfully.
1. 1st year - Good Weather
2nd year - Good Weather
3rd year - Good Weather
4th year- Doesn\' matter as the house would already be constructed.
2. 1st year - Bad weather
2nd year -Good Weather
3rd year - Good Weather
4th year-Good Weather
These are the only two possible ways. We need to find the summation of these two possibilites
1) 1/2 (probability of good weather) * 1/2 (probability of good weather)* 1/2 (probability of good weather) = 1/8
2) 1/2 (probability of bad weather) * 1/2 (probability of good weather) * 1/2 (probability of good weather)* 1/2 (probability of good weather) = 1/ 16.
Hence total probability is (1/8) + (1/16) = 3/16.
Hence the probability that the housing project will be completed in the anticipated 4-year time is 3/16.