Drag the items below and place them in the numbered boxes in
Drag the items below and place them in the numbered boxes in the proper sequence in which decisions are typic
Solution
Process 1: The process would start with the selection of product and service that a firm wants to offer.
Process 2: Then, the facility size and capacity would be analyzed.
Process 3: Facility layout would be prepared.
Process 4: Aggregate plan would be prepared that would convert the business plan into production plan.
Process 5: Disaggregation needs to be performed.
Process 6: Master production schedule would be prepared after disaggregating aggregate plan to the individual level.
Process 7: On the basis of master schedule, material requirements planning (MRP) would be prepared.
Hence, the correct sequence would be as follows: 3>5>6>4>1>7>2