Solution
34. Operating Income of 19000 Units = Sales - VC- FC = 19000 * $4 - 19000 * $1.50 - $17000
Operating Income of 19000 Units = $30500 (Option E)
35. Direct Materials Quantity Variance = (SQ - AQ) * SP
Direct Materials Quantity Variance = (35000 * 3 - 140000) * $1
Direct Materials Quantity Variance = $35000 Unfavourable (Option D)
36. Direct Materials Quantity Variance = (SQ - AQ) * SP
Direct Materials Quantity Variance = (50000 * 6 - 303500) * $2
Direct Materials Quantity Variance = $7000 Unfavourable (Option D)
37. Direct Materials Price Variance = (SP - AP) * AQ
Direct Materials Price Variance = ($5 - $5.10) * 5300
Direct Materials Price Variance = $530 Unfavourable (Option A)
38. $9,750 favorable. Option D
Budgeted direct materials (26000 × $3 each) $ 78000
Unfavorable direct materials variance $16250
Actual cost of direct materials used $ 94250
Standard Cost of Direct Materials Used = AQ × SP = (104000 lb. × $1/lb.) 104000
Direct materials price variance $ 9,750 F