e are preparing a master production schedule for a given item. For this item the demand forecast and booked orders are as follows:
Our Week 0 projected on-hand is 162 units. Lead time for this item is 1 week, and the order policy for this item is a fixed quantity of 300 units. In which weeks are arrival quantities required?
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
| Week | 1 | 2 | 3 | 4 | 5 | 6 |
| Demand Forecast | 80 | 80 | 60 | 60 | 50 | 50 |
| Booked Orders | 58 | 63 | 52 | 20 | 4 | 0 |
Solution
Please find below the filled up MRP table as per data provided:
Lead time of delivery ( i.e. phase lag between quantity received and quantity released ) = 1 week
Fixed order Quantity = 300
WEEK
1
2
3
4
5
6
Booked Order
58
63
52
20
4
0
Projected on hand:162
162
104
41
289
269
265
Ending Inventory
104
41
289
269
265
265
Quantity received
0
0
300
0
0
0
Quantity Released
0
300
0
0
0
0
Here Ending Inventory for a period = Projected on hand for that period – Booked order for that period
Whenever , Projected on hand for a period < Booked order for that period, fixed order quantity of 300 is triggered.
During week 3 , Projected on hand quantity of 41 < Booked order quantity of 52 which should trigger a new order with order quantity of 300. Thus an order quantity of 300 is received in week 3 for which order is released in week 2
Thus arrival quantity is required in week 3
ARRIVAL QUANTITY IS REQUIRED IN WEEK 3
| WEEK | 1 | 2 | 3 | 4 | 5 | 6 |
| Booked Order | 58 | 63 | 52 | 20 | 4 | 0 |
| Projected on hand:162 | 162 | 104 | 41 | 289 | 269 | 265 |
| Ending Inventory | 104 | 41 | 289 | 269 | 265 | 265 |
| Quantity received | 0 | 0 | 300 | 0 | 0 | 0 |
| Quantity Released | 0 | 300 | 0 | 0 | 0 | 0 |