Garret Corporation uses a predetermined overhead rate of 627
Garret Corporation uses a predetermined overhead rate of $62.75 per direct labor-hour. This plantwide predetermined rate was based on a cost formula that estimated $9,412,500 of total manufacturing overhead for an estimated activity level of 150,000 direct labor-hours.
The company incurred actual total manufacturing overhead costs of $9,476,275 and 155,000 total direct labor-hours during the period.
Required:
Determine the amount of manufacturing overhead that would have been applied to all jobs during the period.
Solution
Dear Student,
Best effort has been made to give quality and correct answer. But if you find any issues please comment your concern. I will definitely resolve your query.
Also please give your positive rating.
| Predetermined overhead rate | $ 62.75 |
| Actual Direct Labour Hours | 155,000 |
| Manufacturing overhead Applied (62.75*155000) | $ 9,726,250 |