You have installed 3 250 sq ft of a total 12 165 sq ft of co

You have installed 3, 250 sq. ft. of a total 12, 165 sq. ft. of concrete. What is the percent complete? 8.9% 0 25% 73% none of the above

Solution

Dear Student

Thank you for using Chegg !!

Installed Concrete = 3250 sq ft.

Total concrete = 12165 sq ft

Percentage completion = (3250 / 12165)*100

                                            = 26.72%

Solution

 You have installed 3, 250 sq. ft. of a total 12, 165 sq. ft. of concrete. What is the percent complete? 8.9% 0 25% 73% none of the aboveSolutionDear Student Th