You have installed 3 250 sq ft of a total 12 165 sq ft of co
You have installed 3, 250 sq. ft. of a total 12, 165 sq. ft. of concrete. What is the percent complete? 8.9% 0 25% 73% none of the above
Solution
Dear Student
Thank you for using Chegg !!
Installed Concrete = 3250 sq ft.
Total concrete = 12165 sq ft
Percentage completion = (3250 / 12165)*100
= 26.72%
Solution