the charges to work the charges to work the charges to workS
Solution
Answer:
A)
Total conversion cost
159775
b)
conversion cost per equivalent unit
0.70
c)
. Direct materials cost per equivalent unit
3.70
Working notes for the above answer is as under
a.
Total conversion cost
= $129,4200+$30,355
=$159,775
_________________________________________
b.
Conversion cost per equivalent unit.
Equivalent Unit Produced
= 214,000 + 19000*(3/4)
= 228,250
Conversion cost per equivalent unit
= 159,775/228,250
= $0.70
_____________________________________
C
Whole unit
Direct
material
Conversion
Units started and completed
214,000
100%
214000
100%
214000
Ending work in progress
19000
100%
19000
75%
14250
Total Units accounted for
233,000
233000
228250
Direct material cost per equivalent unit
=862,100/233,000
= $3.70
| A) | Total conversion cost | 159775 |
| b) | conversion cost per equivalent unit | 0.70 |
| c) | . Direct materials cost per equivalent unit | 3.70 |