A Resource 3 B Resource 4 C Resource 1 D Resource 2 Question

A. Resource 3

B. Resource 4

C. Resource 1

D. Resource 2

Question 2 of 11

10.0 Points

A. 8

B. 10

C. 4

D. Cannot be determined

Question 3 of 11

10.0 Points

A. Cannot be determined

B. 90

C. 64

D. 500

Question 4 of 11

10.0 Points

A. 1.75 hours

B. 1.20 hours

C. 1.33 hours

D. 1.60 hours

Question 5 of 11

10.0 Points

A. 1 minute

B. 3 minutes

C. 4 minutes

D. 2 minutes

Question 6 of 11

10.0 Points

A. 2

B. 1

C. 4

D. 3

Question 7 of 11

10.0 Points

A. .1

B. .4

C. 2.5

D. .625

Question 8 of 11

10.0 Points

A. 6

B. 5

C. 3

D. 4

Question 9 of 11

10.0 Points

A. 25%

B. 80%

C. 20%

D. 0%

Question 10 of 11

5.0 Points

A. pushes, demand

B. pulls, capacity

C. pulls, demand

D. pushes, capacity

Question 11 of 11

5.0 Points

A. There is no relationship between the two.

B. The inventory of the process is reduced by adding more Kanban cards.

C. The inventory of the process grows with the square root of the number of Kanban cards.

D. There is no more inventory in the process than was authorized via Kanban cards

A four-step process is used to make a product. The first resource takes 8 minutes per unit, the second takes 7 minutes per unit, the third takes 2 minutes per unit, and the fourth takes 10 minutes per unit. 20% of all units have to be reworked. For that, they have to revisit the third and fourth resources. Each resource is staffed by one worker. Rework takes the same processing times as the first pass and always fixes the problem. Where is the bottleneck?

A. Resource 3

B. Resource 4

C. Resource 1

D. Resource 2

Reset Selection

Question 2 of 11

10.0 Points

C&A uses a two-step process to make a part. The first step involves cutting with a machine that requires a 40-minute setup time before the production of each batch. The cutting takes 30 minutes per part. The second step is polishing the parts from cutting. The polishing takes 40 minutes per part. Assume demand is unlimited. What is the ideal batch size of the parts?

A. 8

B. 10

C. 4

D. Cannot be determined

Reset Selection

Question 3 of 11

10.0 Points

C&A Printing takes 10 seconds to print a page in color, but after 500 pages, the printer must be cooled down for 15 minutes. No pages can be printed while the printer is cooling down. C&A’s demand rate is 3 pages per minute. What is the smallest batch size to ensure the process is demand-constrained?

A. Cannot be determined

B. 90

C. 64

D. 500

Reset Selection

Question 4 of 11

10.0 Points

Packages arrive at a facility at a rate of 30 per hour and are processed continuously at a rate of 25 per hour. The facility is open from 8 a.m. to 4 p.m. How long does the last package wait before it is processed?  

A. 1.75 hours

B. 1.20 hours

C. 1.33 hours

D. 1.60 hours

Reset Selection

Question 5 of 11

10.0 Points

There are 4 servers in the checkout area. The interarrival time of customers is 2 minutes. The processing time is 5 minutes. The coefficients of variation for the arrival process and the service process are 1 and 0.85 respectively. What is the average time in queue?

A. 1 minute

B. 3 minutes

C. 4 minutes

D. 2 minutes

Reset Selection

Question 6 of 11

10.0 Points

There are 3 servers in the checkout area. The interarrival time of customers is 2 minutes. The processing time is 5 minutes. The coefficients of variation for the arrival process and the service process are 1 and 0.85 respectively. What is the average number of customers that are waiting?

A. 2

B. 1

C. 4

D. 3

Reset Selection

Question 7 of 11

10.0 Points

There are 4 servers in the checkout area. The interarrival time of customers is 2 minutes. The processing time is 5 minutes. What is the utilization of the servers?

A. .1

B. .4

C. 2.5

D. .625

Reset Selection

Question 8 of 11

10.0 Points

Consider an Erlang loss system. The average processing time is 4 minutes. The average interarrival time is 3 minutes. How many servers does the system need to achieve a denial of service probability of no more than 0.01?  

A. 6

B. 5

C. 3

D. 4

Reset Selection

Question 9 of 11

10.0 Points

A hardware store rents its one wood chipper. A request for the chipper arrives every 4 days with a standard deviation of 4 days. On average clients rent the chipper for one day. If a request arrives and the chipper is not available, customers rent from another company. What percentage of demand is lost?

A. 25%

B. 80%

C. 20%

D. 0%

Reset Selection

Question 10 of 11

5.0 Points

A kanban system ____________ work through the process based on _________.

A. pushes, demand

B. pulls, capacity

C. pulls, demand

D. pushes, capacity

Reset Selection

Question 11 of 11

5.0 Points

What is the relationship between the number of Kanban cards in a process and the inventory level?

A. There is no relationship between the two.

B. The inventory of the process is reduced by adding more Kanban cards.

C. The inventory of the process grows with the square root of the number of Kanban cards.

D. There is no more inventory in the process than was authorized via Kanban cards

Solution

Please find answer to first 4 questions :

Answer to question 1 :

Effective processing time of any resource = Processing time / unit x ( 1 + percentage of units reworked/ 100 )

Effective processing time of first resource = 8 minutes/ unit

Effective processing time for second resource = 7 minutes/ unit

Effective processing time for third resource = 2 x (1 + 20/100) = 2 x 1.2 minutes = 2.4 minutes /unit

Effective processing time for 4th resource = 10 x ( 1 + 20/100) = 10 x 1.2 = 12 minutes/ unit

Since effective processing time is highest at 4th resource, bottleneck lies there

4TH RESOURCE IS THE BOTTLENECK

Answer to question 2 :

Let, the ideal batch size = N

At ideal batch size, Total processing time for cutting = Total processing time for Polishing ( so that the system is in equilibrium and there is no build up of bottleneck between two processes)

Total processing time for cutting for N units

= Set up time + Total cutting time

= set up time + Cutting time / unit x Number of units

= 40 + 30.N

Total processing time for polishing N units

= Polishing time / unit x Number of units

= 40.N

Therefore, for ideal batch size :

40 + 30.N = 40.N

Or, 10.N = 40

Or, N = 4

IDAL BACTH SIZE OF THE PARTS = 4 UNITS

Answer to question 3 :

To find out the smallest batch size to ensure that the process is demand constrained , we have to find out the batch size and corresponding capacity which at least meets the demand rate of 3 pages per minute or more. ( i.e. Capacity > demand)

Demand rate = 3 pages per minute = 20 seconds / page

Cooling down period for every 500 pages = 15 minutes = 900 seconds

Or , Average cooling down period per page = 900/ 500 = 1.8 seconds / page

Time taken to print per page = 10 seconds

Let the corresponding batch size = N units

Time to print a batch size of N = ( average cooling down period / page + time to print / page ) x N = ( 1.8 + 10 ) x N = 11.8N seconds

Time taken to generate demand for N units = 20.N

Since Capacity should be > Time of corresponding demand of N units,

Total time to print N units < Total time during which demand for N units is generated

11.8N < 20.N

We however cannot determine value of N from above

ANSWER : Cannot be determined

Answer to question 4:

Duration of time when process is open ( 8 AM to 4 PM ) = 8 hours

Total arrival during 8 hours = 30 / hour x 8 hours = 240 packages

Total processed during same 8 hours = 25 / hour x 8 hours = 200 packages

Thus , backlog created after processing for 8 hours i.e. at 4 PM = 240 – 200 = 40 units

Since processing time is 25/hour, time to process this backlog of 40 units = 40 / 25 hour = 1.6 hour

Therefore, last package must wait for 1.6 hours before it is processed

LAST PACKAGE MUST WAIT FOR 1.6 HOURS BEFORE IT IS PROCESSED

4TH RESOURCE IS THE BOTTLENECK

A. Resource 3 B. Resource 4 C. Resource 1 D. Resource 2 Question 2 of 11 10.0 Points A. 8 B. 10 C. 4 D. Cannot be determined Question 3 of 11 10.0 Points A. Can
A. Resource 3 B. Resource 4 C. Resource 1 D. Resource 2 Question 2 of 11 10.0 Points A. 8 B. 10 C. 4 D. Cannot be determined Question 3 of 11 10.0 Points A. Can
A. Resource 3 B. Resource 4 C. Resource 1 D. Resource 2 Question 2 of 11 10.0 Points A. 8 B. 10 C. 4 D. Cannot be determined Question 3 of 11 10.0 Points A. Can
A. Resource 3 B. Resource 4 C. Resource 1 D. Resource 2 Question 2 of 11 10.0 Points A. 8 B. 10 C. 4 D. Cannot be determined Question 3 of 11 10.0 Points A. Can
A. Resource 3 B. Resource 4 C. Resource 1 D. Resource 2 Question 2 of 11 10.0 Points A. 8 B. 10 C. 4 D. Cannot be determined Question 3 of 11 10.0 Points A. Can
A. Resource 3 B. Resource 4 C. Resource 1 D. Resource 2 Question 2 of 11 10.0 Points A. 8 B. 10 C. 4 D. Cannot be determined Question 3 of 11 10.0 Points A. Can
A. Resource 3 B. Resource 4 C. Resource 1 D. Resource 2 Question 2 of 11 10.0 Points A. 8 B. 10 C. 4 D. Cannot be determined Question 3 of 11 10.0 Points A. Can

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site