For the month of February a furniture manufacturer was able
     For the month of February, a furniture manufacturer was able to produce 65 king size beds. He utilized three prime resources: workforce (520 hours for $13 per hour), raw material (100 logs for $5 per log) and equipment (20 days for $50 a day). Calculate multifactor productivity. (provide the answer with six decimal places) Your Answer: | Answer  
  
  Solution
Cost of workforce = Number of hours x Hourly wage rate
= 520 x $13
= $ 6,760
Cost of raw materials = Quantity x Rate
= 100 x $5
= $500
Cost of equipment = Number of days x Rate per day
= 20 x $50
= $ 1,000
So, Total cost = Cost of workforce + Cost of raw materials + Cost of equipment
= $ 6,760 + $500 + $ 1,000
= $8,260
Multifactor productivity
= Output / Total cost of Input
= 65 / $8,260
= 0.007869 per dollar of Input