Costs

Quantities


(a)

Compute the total, price, and quantity variances for materials and labor.

Costs

Actual labor rate $14 per hour
Actual materials price $270 per ton
Standard labor rate $13.50 per hour
Standard materials price $274 per ton

Solution

Material Price Variance = (SP – AP) * Actual Qty

SP = 274

AP = 270

Actual Qty = 1200 tons

   = (274 – 270) * 1200 = 4800(Favourable)

Material Qty Variance = (SQ – AQ) * SP

SQ = 1180 tons

=(1180 – 1200) * 274 = 5480(Unfavourable)

Total Material Variance = Material Price Variance + Material Qty Variance

   = 4800(F) + 5480(U) = 680(Unfavourable)

Labour Price Variance = (SR – AR) * Actual Hrs

SR = 13.50

AR = 14

Actual Hrs = 4900

   = (13.50 – 14) * 4900 = 2450(Unfavourable)

Labour Quantity Variance = (Std Hrs – Actual Hrs) * SR

Std Hrs = 4980

= (4980 – 4900) * 13.50 = 1080(Favourable)

Total Labour Varaince = Labour Price Variance + Labour Quantity Variance

= 2450(U) + 1080(F) = 1370(Unfavourable)