A machine can operate for an average of 3 weeks before it needs to be overhauled, a process which takes 5 days. The machine is operated 6 days a week. Compute the availability of this machine. Round answer to three decimal. Please show all work
Solution
Availability of machine = Operating time /Calender time
= 18 days/ 21 days
=86% is the availability of this machine.
Explanation:
Operating time =6 days *3 weeks = 18 days
Calender time = 7 days * 3 weeks = 21 days