039 If EV 300 AC 400 and the project bu the project this i
039. If EV = $300, AC = $400, and the project bu the project (this is known as EAC, estimate at complete)? dget is $1,000, what is the estimated final cost of a. $750 b. $1,000 C. $1,250 d. $1,333
Solution
d-Cost Performance Index (CPI) = EV / AC= 300/400=0.75
BAC= $1000
EAC = BAC / CPI = 1000/0.75= $1333