You track a project as scheduled by updating work to the u t
You track a project as scheduled by updating work to the. u track a project as scheduled by updating work to the date of your first milestone delivery date of the next planned stakeholders meeting date you created your baseline current date
Solution
th etrack project as scheduled by updating work to the date of cration of baseline.
hence the answer option is \" date you created your baseline\"