The question is in the last photo Example Shopping Mall Reno
The question is in the last photo
Solution
Z=(Expected time-Project time)/sqrt(variance of critical path)
Z= normisinv(Probability)
=normsinv(0.95)
= 1.644854
Project time= Time of completion of ADEFHG= 3+7+2+3+16+4=35
From 1st equation
1.644854=(Expected time- 35)/sqrt( 0.44+1.78+0.11+0.44+1.78+0.440)
Hence expected time= 38.67