QUESTION6 The following standards for variable one product o
Solution
Question 6
Variable Overhead Efficiency Variance
Standard Hours Allowed for actual production:
Actual Production
4,000
Units
x Allowed Standard Hours Per Unit
1.2
Hours
Total Standard Hours Allowed for actual production (SHAP)
4800
Hours
Actual Hours Worked (AH)
5000
Hours
Variance or Difference in Hours
200
hours
x Standard Hourly Variable Overhead Rate
$10.20
per hour
Variable Overhead Efficiency Variance
$2,040
Unfavorable
The correct option is $2,040 U.
Here the Actual Hours worked is higher than anticipated hours to be worked to get actual production units, hence the variance is Unfavorable.
Question 7
The correct option is Sunk Cost.
Sunk Cost is the cost which has already been incurred in the past and does not have any impact on the decision making. Sunk costs are irrelevant.
Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you
| Standard Hours Allowed for actual production: | ||
| Actual Production | 4,000 | Units |
| x Allowed Standard Hours Per Unit | 1.2 | Hours |
| Total Standard Hours Allowed for actual production (SHAP) | 4800 | Hours |
| Actual Hours Worked (AH) | 5000 | Hours |
| Variance or Difference in Hours | 200 | hours |
| x Standard Hourly Variable Overhead Rate | $10.20 | per hour |
| Variable Overhead Efficiency Variance | $2,040 | Unfavorable |

