6 people can pick 80 quarts of blueberries in one day The ma
6 people can pick 80 quarts of blueberries in one day. The manager gets an order of 280 quarts that are to be picked within 3 days. How many total people does he need to employ for the three day period?
Solution
6 people can pick 80 quarts in 1 day
 1 people can pick 80/6 = 40/3 quarts in 1 day
to pick 280 quarts in 3 days, number of people= 280/(3*40/3)
 = 280/40
 = 7 people
 Answer: 7 people