People Window Help Take a Test Danialee Ortega Secure rTest.aspx?testid 176857 MGT 325: Business Processes and Supply Chain Management Dwialee Ortega1 1/31/18 11:25 Quiz: Quiz 01 Spring 2018 Time Remaining: 00.09:13 Submit This Question: 3 pts 70, 14(11 complete) This Quiz: 30 pts pos Bums Boats wants to assemble 40 boats per 13-hour day, using a production line. Total task Sime for each bost is 20 minutes a.The takt time isnnnes per boat. (Enter your response eunded to one dena, ace) The theoretical minimum number of workstations isEnter your response rounded up to the next whole number) b. Suppose the longest individual task takes 27 minutes. Wil Bums be able to accomplish its goa? O A. Yes because the longest task time is less than the takt time. The takt Sme is equal to the highest alowable cycle time in order to meet the required output rate OB. No because the longest task sme is larger han the takt The tait tino s equal te the highest alowatie cycle tine n order to meet to mired output OC. Yes because the longest task timis less than the total task time tor each boat. O D. Yes because the longest task time is larger than the takt time. The takt tme is equal to the lowest allowable cycle ime in onder to meet the required output Click to select your answerls MacBook Air 4 5 7 8 0

Solution

A) The TAKT time would technically be

13*60 Minutes per day

40boats to be produced

Takt time= 13*60/40= 19.5 Minutes

as the Task time is 20 Minutes per boat

Hence the required minimum number of workstations would be 2

B) No, Because the longest task time is greated than the Takt time

 People Window Help Take a Test Danialee Ortega Secure rTest.aspx?testid 176857 MGT 325: Business Processes and Supply Chain Management Dwialee Ortega1 1/31/18

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site