Compute the PI statistic for Project Q if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)
| Compute the PI statistic for Project Q if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) |
Solution
Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)
=3650/1.12+4480/1.12^2+1820/1.12^3+2450/1.12^4
=$9682.816486
NPV=Present value of inflows-Present value of outflows
=$9682.816486-$11600
=($1917.183514)
PI=NPV/Present value of outflows
=(1917.183514)/11600
=(0.17)(Approx) or (16.52)%(Approx)(Negative)
Hence since PI is negative;project must be rejected.