The following jobs are available for processing at time 0 If

The following jobs are available for processing at time 0:

If the Shortest Processing Time rule is used to prioritize work through this work center, and assuming no new jobs arrive while these jobs are being processed, what will be the average job flowtime in this situation?

Job Req\'d Process Time (hrs)
A 27
B 13
C 20
D 7
E 24

Solution

The average job flow time refers to the average time taken by the job and the Waiting time involved in it . It is also a tool used to measure the effectiveness of scheduling as it states the efficiency of process scheduled which process involves less waiting time .

Average flow time =( total process time + total waiting time) ÷ total number of jobs

= (7+13+20+24+27) ÷ 5

= 18.2 hrs