Complete MRP What can be done in weeks 10 and 11SolutionAssu

Complete MRP. What can be done in weeks 10 and 11?

Solution

Assumption

1) Safety stock requirement is 400. So For maintaining the safety stock level we have to order Safety stock separately. That order is placed in 8 th week.

2) Projected balance is 1000 . So demand of 10 th week can be managed from projected balance.

3)Lead time is 2 weeks .So for every week the order placed before 2 weeks.

4) Net requirement is the requirement of the respective demand of that week.

5) Safety stock is maintained 400 in 17 th week

6) As per asked in problem , Lot for Lot techniques is used.

MRP Table

Lead Time 2 weeks Week
8 9 10 11 12 13 14 15 16 17
Gross Requirement 0 0 1000 0 1300 800 0 1400 900 0
Projected Balance 1000 0
Saftey 0 0 400 400 400 400 400 400 400 400
Scheduled Receipt 400(For Saftey Stock) 0 1300 800 1400 900
Net Requirements 0 0 1000 0 1300 800 0 1400 900 0
Planned Order Receipts 400(For Saftey Stock) 0 1300 800 0 1400 900 0 0 0
Planned Order Releases 400(For Saftey Stock) 0 1300 800 0 1400 900 0 0 0
Complete MRP. What can be done in weeks 10 and 11?SolutionAssumption 1) Safety stock requirement is 400. So For maintaining the safety stock level we have to or