Question 1 A critical path refers to a sequence of task acti

Question 1

A critical path refers to:

a sequence of task activities whose order and durations indirectly affect the completion date of a project.

a sequence of task activities whose order and durations directly affect the completion date of a project.

a sequence of task activities whose order must be performed in parallel.

a sequence of task activities whose duration cannot last more than 40 percent of the time allotted to the project.

None of these.

1 points

Question 2

A scheduling technique where the order and duration of the sequence of activities directly affect the completion date of a project refers to:

critical path scheduling.

Gantt scheduling.

task management.

activity scheduling.

sequencing strategy.

1 points

Question 3

A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task best defines:

flowcharting.

Unified Modeling Language (UML).

Gantt.

Program Evaluation Review Technique (PERT).

Computer Aided Software Engineering (CASE).

1 points

Question 4

An example of a project management system is:

Microsoft Project for Windows.

Microsoft Office.

QuarkXpress.

Word Perfect.

Lotus 1-2-3.

1 points

Question 5

Any person, group of people, piece of equipment, or material used in accomplishing an activity is referred to as a(n):

expense.

agent.

identifier.

entity.

resource.

1 points

Question 6

Automated tools available to help you manage a development project are referred to as:

diagram generators.

utility software.

desktop publishing software.

project management software.

systems development software.

1 points

Question 7

Changes to the baseline project plan might be motivated by:

a slipped completion date of an activity.

a bungled activity that must be redone.

the identification of a new activity that becomes evident later in the project.

an unforeseen change in personnel due to sickness, resignation, or termination.

All of these.

1 points

Question 8

Determining the strengths and weaknesses of project deliverables, the processes used to create them, and the project management process is done during:

closing the customer contract.

establishing the communication plan.

conducting post project reviews.

communicating the project status.

closing down the project.

1 points

Question 9

Developing an understanding of the content and complexity of the project is the purpose of:

determining project standards and procedures activity of the project planning phase.

describing the project scope, alternatives, and feasibility activity of the project planning phase.

setting a baseline project plan activity of the project planning phase.

closing down the project activity of the project planning phase.

developing a project charter activity of the project planning phase.

1 points

Question 10

During which of the following project planning activities do you use the information regarding tasks and resource availability to assign time estimates to each activity in the work breakdown structure?

Dividing the project into manageable tasks

Developing a preliminary schedule

Developing a project scope statement

Describing project scope, alternatives, and feasibility

Setting a baseline project plan

1 points

Question 11

Ensuring that all contractual terms of the project have been met is done during:

setting a baseline project plan.

conducting post project reviews.

communicating the project status.

closing the customer contract.

project implementation.

1 points

Question 12

Identifying, assessing, and managing the risks and day-to-day changes that occur during a project best defines which of the following project manager activities?

Customer relations

Risk and change management

Conflict management

Technical problem solving

Team management

1 points

Question 13

Indicating when and how written and oral reports will be provided by the team, how team members will coordinate work, what messages will be sent to announce the project to interested parties, and what kinds of information will be shared with vendors and external contractors involved with the project describes:

developing a project scope statement.

establishing the project initiation team.

determining project standards and procedures.

developing a communication plan.

setting a baseline project plan.

1 points

Question 14

Influencing the activities of others toward the attainment of a common goal through the use of intelligence, personality, and abilities refers to which of the following project manager activities?

Management

Conflict management

Customer relations

Team management

Leadership

1 points

Question 15

Managing conflict within a project team to ensure that conflict is not too high or too low best defines which of the following project manager activities?

Risk management

Leadership

Conflict management

Team management

Problem solving

1 points

Question 16

Skills that include defining and sequencing activities, communicating expectations, assigning resources to activities, and monitoring outcomes best represent:

management.

team management.

leadership.

technical problem solving.

customer relations.

1 points

Question 17

The amount of time that an activity can be delayed without delaying the project refers to:

slack time.

delay time.

stop time.

down time.

noncritical time.

1 points

Question 18

The final phase of the project management process that focuses on bringing a project to an end is called:

project initiation and planning.

project closedown.

project evaluation.

project implementation.

project review.

1 points

Question 19

The process of dividing the project into manageable tasks and logically ordering them to ensure a smooth evolution between tasks defines:

work breakdown structure.

work structuring.

task division.

critical path scheduling.

project division.

1 points

Question 20

The responsibility for keeping all team members informed of the project status best describes:

updating project status.

monitoring project progress against the baseline project plan.

communicating the project status.

executing the baseline plan.

establishing the project initiation plan.

1 points

Question 21

Which of the following is NOT a task characteristic?

A task should have well-accepted predecessor and successor steps.

A task should have a known method or technique.

A task should be completed by only one person.

A task is measurable so that percent completed can be determined.

A task should have a single and identifiable deliverable.

1 points

Question 22

Which of the following is NOT a true statement regarding network diagrams?

All activities with a slack time equal to zero are on the critical path.

To construct a network diagram, a horizontal bar is drawn for each activity that reflects its sequence and duration.

Nodes not on the critical path can be delayed (for some amount of time) without delaying the final completion of the project.

The critical path of a network diagram is represented by the sequence of connected activities that produce the longest overall time period.

The latest expected completion time refers to the time in which an activity can be completed without delaying the project.

1 points

Question 23

Which of the following is a true statement regarding project time estimates?

Hardware and software are the most important, and expensive, part of project resource planning.

Project time estimates are always on target.

Project time estimates for task completion and overall system quality are significantly influenced by the assignment of people to tasks.

Resource estimates should not be revised based upon the skills of the actual person assigned to a particular activity.

Staff learning can be enhanced by assigning individuals to tasks which are \"over their heads.\"

1 points

Question 24

Which of the following is true regarding Gantt chart construction?

To construct the Gantt chart, a horizontal bar is drawn for each activity that reflects its sequence and duration.

Ellipses are used to represent activities.

To show precedence relationships, arrows are used to connect the nodes.

Arrows are used to reflect the sequence of activities.

Squares are used to represent activities.

1 points

Question 25

Which of the following refers to the time in which an activity can be completed without delaying the project?

Latest expected completion time

End time

Earliest expected completion time

Critical time

Delay time

a sequence of task activities whose order and durations indirectly affect the completion date of a project.

a sequence of task activities whose order and durations directly affect the completion date of a project.

a sequence of task activities whose order must be performed in parallel.

a sequence of task activities whose duration cannot last more than 40 percent of the time allotted to the project.

None of these.

Solution

Please follow the data and description :

1) A critical path refers to a term that is related to the field of project management describing a set of tools and a methodology. In a simpler term, the critical path is the sequence of tasks that will take the longest to complete to deliver the project.

So the answer is OPTION B (a sequence of task activities whose order and durations directly affect the completion date of a project.)

2) A scheduling technique where the order and duration of the sequence of activities directly affect the completion date of a project refers to the critical path scheduling.

So the answer is OPTION A (critical path scheduling).

3) A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task best defines the Program Evaluation Review Technique (PERT).

So the answer is OPTION D (Program Evaluation Review Technique (PERT).)

4) An example of a project management system is Microsoft Project for Windows.

So the answer is OPTION A (Microsoft Project for Windows.)

5) Any person, group of people, piece of equipment, or material used in accomplishing an activity is referred to as a(n) is a resource.

So the answer is OPTION E (resource).

6) Automated tools available to help you manage a development project are referred to as project management software.

So the answer is OPTION D (project management software.).

7) Changes to the baseline project plan might be motivated by a slipped completion date of an activity, a bungled activity that must be redone, the identification of a new activity that becomes evident later in the project, an unforeseen change in personnel due to sickness, resignation, or termination.

So the answer is OPTION E (All of these).

8) Determining the strengths and weaknesses of project deliverables, the processes used to create them, and the project management process is done during conducting post project reviews.

So the answer is OPTION C (conducting post project reviews.)

9) Developing an understanding of the content and complexity of the project is the purpose of describing the project scope, alternatives, and feasibility activity of the project planning phase.

So the answer is OPTION B (describing the project scope, alternatives, and feasibility activity of the project planning phase.)

10) Developing a preliminary schedule, project planning activities do you use the information regarding tasks and resource availability to assign time estimates to each activity in the work breakdown structure

So the answer is OPTION B (Developing a preliminary schedule)

11) Ensuring that all contractual terms of the project have been met is done during closing the customer contract.

So the answer is OPTION D (closing the customer contract.)

12) Identifying, assessing, and managing the risks and day-to-day changes that occur during a project best defines which of the following project manager activities Risk and change management.

So the answer is OPTION B (Risk and change management).

13) Indicating when and how written and oral reports will be provided by the team, how team members will coordinate work, what messages will be sent to announce the project to interested parties, and what kinds of information will be shared with vendors and external contractors involved with the project describes developing a communication plan.

So the answer is OPTION D (developing a communication plan.).

14) Influencing the activities of others toward the attainment of a common goal through the use of intelligence, personality, and abilities refers to which of the following project manager activities - Leadership.

So the answer is OPTION E (Leadership).

15) Managing conflict within a project team to assure that conflict is not too high or too low describes the conflict management project manager activity

So the answer is OPTION C (Conflict management)

16) Skills that include defining and sequencing activities, communicating expectations, assigning resources to activities, and monitoring outcomes best represent management skill.

So the answer is OPTION A (Management)

17) the amount of time an activity can be delayed without delaying the early start of any immediately following activities slack time.

So the answer is OPTION A (slack time.)

18) The final phase of the project management process that focuses on bringing a project to an end is called project closedown.

So the answer is OPTION B (project closedown.)

19) The process of dividing the project into manageable tasks and logically ordering them to ensure a smooth evolution between tasks defines work breakdown structure.

So the answer is OPTION A (work breakdown structure.)

20) The responsibility for keeping all team members informed of the project status best describes communicating the project status.

So the answer is OPTION C (communicating the project status.)

21) Which of the following is NOT a task characteristic A task should be completed by only one person.

So the answer is OPTION C (A task should be completed by only one person.)

22) Which of the following is NOT a true statement regarding network diagrams :

To construct a network diagram, a horizontal bar is drawn for each activity that reflects its sequence and duration.

So the answer is OPTION B (To construct a network diagram, a horizontal bar is drawn for each activity that reflects its sequence and duration.)

23) Which of the following is a true statement regarding project time estimates :

Project time estimates for task completion and overall system quality are significantly influenced by the assignment of people to tasks.

So the answer is OPTION C (Project time estimates for task completion and overall system quality are significantly influenced by the assignment of people to tasks.)

24) Which of the following is true regarding Gantt chart construction :

To construct the Gantt chart, a horizontal bar is drawn for each activity that reflects its sequence and duration.

So the answer is OPTION A(To construct the Gantt chart, a horizontal bar is drawn for each activity that reflects its sequence and duration.)

25) Which of the following refers to the time in which an activity can be completed without delaying the project :

Latest expected completion time

So the answer is OPTION A (Latest expected completion time).

Hope this is helpful.

Question 1 A critical path refers to: a sequence of task activities whose order and durations indirectly affect the completion date of a project. a sequence of
Question 1 A critical path refers to: a sequence of task activities whose order and durations indirectly affect the completion date of a project. a sequence of
Question 1 A critical path refers to: a sequence of task activities whose order and durations indirectly affect the completion date of a project. a sequence of
Question 1 A critical path refers to: a sequence of task activities whose order and durations indirectly affect the completion date of a project. a sequence of
Question 1 A critical path refers to: a sequence of task activities whose order and durations indirectly affect the completion date of a project. a sequence of
Question 1 A critical path refers to: a sequence of task activities whose order and durations indirectly affect the completion date of a project. a sequence of
Question 1 A critical path refers to: a sequence of task activities whose order and durations indirectly affect the completion date of a project. a sequence of
Question 1 A critical path refers to: a sequence of task activities whose order and durations indirectly affect the completion date of a project. a sequence of
Question 1 A critical path refers to: a sequence of task activities whose order and durations indirectly affect the completion date of a project. a sequence of