The following data has been provided by Moretta Corporation
The following data has been provided by Moretta Corporation, a company that produces forklift trucks:
Budgeted production 3400 trucks
Standard machine-hours per truck 2.9 machine-hours
Standard supplies cost $1.50 per machine hour
Actual production 3800 trucks
Actual machine-hours 10930 machine-hours
Actual supplies cost (total) $17496
Supplies cost is an element of variable manufacturing overhead. The variable overhead efficiency variance for supplies cost is:
A) $135 U
B) $135 F
C) $966 U
D) $966 F
Solution
B) $135 F Standard Actual Particulars Hours Rate amount Hours Rate amount Overhead 11,020.00 1.50 16,530.00 10,930.00 1.6007 17,496.00 Actual output 3,800.00 Labour hrs reqd (3800 * 2.9) 11,020.00 VOEV = (SH-AH)SR VOEV = (11,020 - 10,930)1.50 VOEV = (90)1.50 VOEV = 135 F