Following table illustrates average time for each activity for each of the two workers .

Average time of an activity = Sum of 5 sets of data for each activity / 5

Times - Worker 1 ( Minutes)

Times - Worker 2 ( Minutes )

Activity

1

2

3

4

5

Average ( Minutes)

1

2

3

4

5

Average ( Minutes)

Check material and store in warehouse

15.7

16.2

15.9

16.5

16.7

16.2

17.4

18.1

17.9

18.1

17.5

17.8

Move material to the assembly line

7.6

7.4

6.9

7.3

7

7.24

6.7

5.9

6.9

6.5

6.1

6.42

Production in assembly line

20.2

19.8

20.1

18.9

18.7

19.54

16.9

17.5

17.3

16.8

17.4

17.18

Quality control in assembly line

3.7

4.2

4.6

3.9

4.4

4.16

5.3

5.3

4.9

5

5.3

5.16

Store product in boxes

5.7

6.2

6

5.8

8.9

6.52

4.6

4.9

4.5

5.2

5

4.84

Deliver to customers

17.2

16.7

17.5

16.9

17.1

17.08

15.9

16.2

15.8

16.5

15.6

16

TOTAL:

70.74

TOTAL:

67.4

The sum of all activities for worker 1 = 70.74 minutes per unit

The sum of all activities for worker 2 = 67.4 minutes per unit

TIME FOR WORKER 1 =      70.74 MINUTES PER UNIT

TIME FOR WORKER 2 = 67.4 MINUTES PER UNIT

AVERAGE TIME = ( 70.74 + 67.4)/2 = 69.07 MINUTES PER UNIT

Productivity for worker 1 = 60/70.74 units per hour = 0.848 units per hour

Productivity for worker 2 = 60/67.4 units per hour = 0.890 units per hour

Average Productivity = ( 0.848 + 0.890 )/2 units per hour = 0.869 units per hour

Gross salary of Euro 10.5 per hour needs to be distributed amongst 2 workers based on their productivities. Higher the productivity , more will be the salary.

Thus ,

Salary for worker 1 =   0.848 / ( 0.848 + 0.890) x 10.5 = 0.848 x 10.5/ 1.738 = Euro 5.123

Salary for Worker 2 = 0.890 / ( 0.848 + 0.890) x 10.5 = 0.890 x 10.5/ 1.738 = Euro 5.377

Times - Worker 1 ( Minutes)

Times - Worker 2 ( Minutes )

Activity

1

2

3

4

5

Average ( Minutes)

1

2

3

4

5

Average ( Minutes)

Check material and store in warehouse

15.7

16.2

15.9

16.5

16.7

16.2

17.4

18.1

17.9

18.1

17.5

17.8

Move material to the assembly line

7.6

7.4

6.9

7.3

7

7.24

6.7

5.9

6.9

6.5

6.1

6.42

Production in assembly line

20.2

19.8

20.1

18.9

18.7

19.54

16.9

17.5

17.3

16.8

17.4

17.18

Quality control in assembly line

3.7

4.2

4.6

3.9

4.4

4.16

5.3

5.3

4.9

5

5.3

5.16

Store product in boxes

5.7

6.2

6

5.8

8.9

6.52

4.6

4.9

4.5

5.2

5

4.84

Deliver to customers

17.2

16.7

17.5

16.9

17.1

17.08

15.9

16.2

15.8

16.5

15.6

16

TOTAL:

70.74

TOTAL:

67.4

 15.7 16.2 15.9 16.5 16.7 17.4 18.1 17.9 18.1 17.5 7.6 7.4 6.9 7.3 7.0 6.7 5.9 6.9 6.5 6.1 20.2 19.8 20.1 18.9 18.7 16.9 17.5 17.3 16.8 17.4 3.7 | 4.2 | 4.6 | 3
 15.7 16.2 15.9 16.5 16.7 17.4 18.1 17.9 18.1 17.5 7.6 7.4 6.9 7.3 7.0 6.7 5.9 6.9 6.5 6.1 20.2 19.8 20.1 18.9 18.7 16.9 17.5 17.3 16.8 17.4 3.7 | 4.2 | 4.6 | 3
 15.7 16.2 15.9 16.5 16.7 17.4 18.1 17.9 18.1 17.5 7.6 7.4 6.9 7.3 7.0 6.7 5.9 6.9 6.5 6.1 20.2 19.8 20.1 18.9 18.7 16.9 17.5 17.3 16.8 17.4 3.7 | 4.2 | 4.6 | 3
 15.7 16.2 15.9 16.5 16.7 17.4 18.1 17.9 18.1 17.5 7.6 7.4 6.9 7.3 7.0 6.7 5.9 6.9 6.5 6.1 20.2 19.8 20.1 18.9 18.7 16.9 17.5 17.3 16.8 17.4 3.7 | 4.2 | 4.6 | 3

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site