Bell & Porter has the following average times (in hours):
 Inspecting product 0.30
 Manufacturing product 2.10
 Storing inventory 0.35
 Transporting product 3.25
Required:
Calculate the manufacturing cycle efficiency.
Solution
Manufacturing cycle efficiency = Processing time / (Processing time + Moving time + Storing time + Inspection time)
= 2.10 hrs / (2.10 hrs + 3.25 hrs + 0.35 hrs + 0.30 hrs)
= 2.10 hrs / 6.00 hrs
= 35%