Question 2 The cash flows for two alternatives are as follow

Question 2 The cash flows for two alternatives are as follows: Year Alternative A 30,000 12,000 9,000 6,000 3,000 Alternative B 35,000 1,000 4,000 7,000 10,000 13,000 6.000 19,000 22.000 (a) Based on payback period, which alternative should be selected? (b) Using present worth analysis, and a 12% interest rate which alternative should be selected? (c) If the answers in (a) and (b) differs, explain why?

Solution

(Question 2)

(a) Payback period (PBP) is the time by when a project\'s cumulative cash flows equal zero.

For Alternative A, PBP is 4 years. For Alternative B, PBP is 5 years. Since alternative A has lower PBP, this should be selected.

(b) Present worth (PW) of both alternatives is computed as follows.

Since alternative B has higher (and positive) PW, this should be selected.

(c) As per PBP method, Alternative A is selected and as per PW method, alternative B is preferred. This is because alternative A has higher cash flows in earler years and alternative B has higher cash flows in later years, which are ignored by the PBP Method.

NOTE: As per Chegg answering guidelines, 1st question is answered in full.

Alternative - A
Year Cash flow Cumulative cash flow
0 -30,000 -30,000
1 12,000 -18,000
2 9,000 -9,000
3 6,000 -3,000
4 3,000 0
Alternative - B
Year Cash flow Cumulative cash flow
0 -35,000 -35,000
1 1,000 -34,000
2 4,000 -30,000
3 7,000 -23,000
4 10,000 -13000
5 13,000 0
 Question 2 The cash flows for two alternatives are as follows: Year Alternative A 30,000 12,000 9,000 6,000 3,000 Alternative B 35,000 1,000 4,000 7,000 10,000

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site