A crew of 5 carpenters and 2 laborers will be used to build
Solution
Actual Hour = ( 10 hr/day x 5 days) + ( 7 hr/day x 1 days) = 57 hr.
Pay Hour = weekly straight time +weekly overtime+ Saturday overtime
= ( 5 days x 8 hrs/day @1.0) + ( 5 days x 1 hrs/day @1.5) + ( 1 day x 8 hrs/day x 2.0)
= 40+7.5+16.0
= 63.5 hr
Average hourly hour = [pay hour / Actual hour] x Base wage
Carpenter Cost
Average hourly hour = (63.5 / 57) x $32.50/hr = $ 36.206140/hr
Social security tax = 7.65 % x $ 36.206140/hr = 2.76976971
State unemployment = 3.0% x $ 36.206140/hr = 1.0861842
Federal unemployment = 2.0% x $ 36.206140/hr = 0.7241228
Workers Compensation = $4.75/ $100.00 x $32.50/hr = 1.54375
Public liability/property damage = $2.20/ $100.00 x $32.50/hr = 0.715
Fringe benefits = 2.10
carpenter average hourly cost = $ 45.14496671
carpenter hourly cost = $ 45.14/hour
carpenter weekly cost = $ 45.14496/hr x 53.0 hr/week = $ 2392.68288/week
carpenter monthly cost = $ 2392.68288/week x 52/12 = $10368.29/month
Labour Costs -
Average hourly hour = (63.5 / 57) x $24.00/hr = $ 26.736 /hr
Social security tax = 7.65 % x $ 26.736/hr = 2.045304
State unemployment = 3.0% x $ 26.736/hr = 0.80208
Federal unemployment = 2.0% x $ 26.736/hr = 0.53472
Workers Compensation = $3.5/ $100.00 x $24.00/hr = 0.84
Public liability/property damage = $1.80/ $100.00 x $24.00/hr = 0.432
Fringe benefits = 1.75
laborer average hourly cost = $ 33.140104
laborer hourly cost = $ 33.14/hour
laborer weekly cost = $ 33.140104/hr x 53.0 hr/week = $ 1756.425512 /week
laborer monthly cost = $ 1756.425512/week x 52/12 = $ 7611.17721 /month
Crew costs
Hourly cost of crew = 5 carpenters @ $ 45.14/hr + 2 laborer @ $ 33.14/hr = $ 291.98/hr
Weekly cost of crew = 5 carpenters @ 2392.68288/week + 2 laborer @ $ 1756.425512 /week = $ 15476.265424/ week
Monthly cost of crew = 5 carpenters @ $10368.29/month + 2 laborer @ $ 7611.17721 /month = $ 67063.80442/ month.