1 Suppose a gun manufacturers demand is 34400 parts per mont
1. Suppose a gun manufacturer’s demand is 34,400 parts per month. The company works 5 days per week and on average 20 days per month. There are two, eight hour shifts. Lunch is 30 minutes per shift. Two, ten minute breaks are taken per shift. Calculate the takt time.
0.5 minutes/unit
2.5 minutes/unit
1500 seconds/unit
2.6 minutes/unit
| 0.5 minutes/unit | ||
| 2.5 minutes/unit | ||
| 1500 seconds/unit | ||
| 2.6 minutes/unit |
Solution
Minutes available per shift = 8hrs x 60 minutes - 30 minutes - 10 minutes - 10 minutes
= 430 minutes
Minutes available in two shifts = 430 x 2 = 860 minutes
Minutes available per month = 860 x 20 = 17,200 minutes
So, minutes per unit = 17,200 / 34,400
= 0.5 minutes/unit
So, option A is the correct option.