Because of its labor contract a company must hire enough lab
Solution
Total production required = Ending inventory + sum of forecast demand – Opening inventory = 300 + 1080 – 200 = 1180
Since week 2 is cut to half, total number of weeks available for production = 5.5 weeks
It is however mentioned that maximum available normal monthly production = 200
Thus, total normal production in 5.5 weeks = 200 x 5.5 = 1100 units
Thus , shortfall which needs to be catered from extra production during week 4 = 1180 – 1100 = 80 units
It is to be note that maximum “upto 100 units” can be produced in week 4 .
Since production requirement of 80 < Maximum additional production available of 100 units, it is a feasible plan
Thus Production plan would be as per following:
Week 1 = 200 units
Week 2 = 100 units
Week 3 = 200 Units
Week 4 = 200 + 80 = 280units
Week 5 = 200 units
Week 6 = 200 units
Week
1
2
3
4
5
6
Total
Forecast demand
120
160
240
240
160
160
1080
Planned production
200
100
200
280
200
200
1180
Planned inventory :200
280
220
180
220
260
300
| Week | 1 | 2 | 3 | 4 | 5 | 6 | Total |
| Forecast demand | 120 | 160 | 240 | 240 | 160 | 160 | 1080 |
| Planned production | 200 | 100 | 200 | 280 | 200 | 200 | 1180 |
| Planned inventory :200 | 280 | 220 | 180 | 220 | 260 | 300 |

