7 If a drywall guy has to hang 400 sheets of drywall and his
7. If a drywall guy has to hang 400 sheets of drywall and his productivity rate is 0.296. How many labor hours are required?
Solution
7.
Labor productivity is the value of goods and services produced in a period of time, divided by the hours of labor used to produce them. In other words, labor productivity measures output produced per unit of labor.
SO productivity = .296 = (total sheets to hang)/(time take in hours to hang all the sheets)
=> .296 = 400/t
=> t = 400/.296 = 1351.35 hours
hence the drywall guy would take 1351.35 hours to hang 400 sheets of drywall.