Question 54 was previously answered incorrectly I would like
Question 5.4 was previously answered incorrectly. I would like to understand this problem better. Please double check work.
Using the following data, develop an allowance percentage for a job element that requires the worker to lift a weight of 15 pounds while (1) standing in a slightly awkward position, (2) in light that is well below recommended standards, and (3) with intermittent very loud noises occurring. The monotony for this element is medium. Include a personal allowance of 5 percent and a basic fatigue allowance of 4 percent of job time. (Leave no cells blank - be certain to enter \"0\" wherever required. Omit the \"%\" sign in your response.)
| Using the following data, develop an allowance percentage for a job element that requires the worker to lift a weight of 15 pounds while (1) standing in a slightly awkward position, (2) in light that is well below recommended standards, and (3) with intermittent very loud noises occurring. The monotony for this element is medium. Include a personal allowance of 5 percent and a basic fatigue allowance of 4 percent of job time. (Leave no cells blank - be certain to enter \"0\" wherever required. Omit the \"%\" sign in your response.) |
Solution
Explanation:
while estimating standard time of doing a job , some extra allowances are provided on the basis of nature of work.
so different factors are taken in to consideration like standing, bad light , noise level, monotony etc...
Factors :
| Factor | % |
| Personal | 5 |
| Fatigue | 4 |
| Standing | 2 |
| Lifting | 2 |
| Bad Light | 2 |
| Noise Level | 5 |
| Monotony | 1 |
| Total | 21 |