CLMheducation owconnecthtml Good To Saved Help Save Exit S

CLMheducation ow/connect.html Good To ? Saved Help Save & Exit Submit Cardero Midwifery\'s cost formula for its wages and salaries is $2.280 per month plus $348 per birth. For the month of August, the company planned for activity of 118 births, but the actual level of activity was 116 births. The actual wages and salaries for the month was $44,120. The wages and salaries in the planning budget for August would be closest to Multiple Choice $43,344 $42,648 $44,881 Next $44,120 of 33 IS

Solution

ANSWER --- $42,648 (b)

wages and salaries =$2280 per month

wages and salaries per birth = $348

actual level of activity = 116 births

wages and salaries in the planning budget for August = $2280 + $(348*116) = $42,648

 CLMheducation ow/connect.html Good To ? Saved Help Save & Exit Submit Cardero Midwifery\'s cost formula for its wages and salaries is $2.280 per month plus

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site