Need help creating Network Diagram and Critical Path for Hen
Need help creating Network Diagram and Critical Path for...
Hence the total time required is 62-7 = 55
| Brush teeth | 2 |
| Shower | 5 |
| Blow dry and do hair | 10 |
| Prepare coffee (just preparation) | 3 |
| Boil four eggs (soft boiled) | 6 |
| Get dressed | 4 |
| Put on make-up | 10 |
| Eat breakfast | 15 |
| Coffee percolates (this is an activity that does not require Allison\'s time) | 7 |
Solution
Ans-
The Project Management Body of Knowledge (PMBOK), an internationally recognized collection of processes and knowledge areas accepted as best practice for the project management profession, defines the critical path as “the sequence of scheduled activities that determines the duration of the project.” It is the longest sequence of tasks in a project plan that must be completed on time in order for the project to meet its deadline. If there is a delay in any task on the critical path, then your whole project will be delayed. Although many projects have only one critical path, some projects may have multiple critical paths.
The critical path method is a step-by-step project management technique to identify activities on the critical path. It is an approach to project scheduling that breaks the project into several work tasks, displays them in a flow chart, and then calculates the project duration based on estimated durations for each task. It identifies tasks that are critical, time-wise, in completing the project.
In any given project, you may have hundreds of tasks and dozens of dependencies. It can feel almost impossible to identify the most important tasks; the ones that, if missed, will impact your whole project. In other words, the ones you really need to worry about to make sure you meet your deadlines.
The critical path method, a project management technique created in the 1950s, allows you to identify these important tasks and stay on track throughout your project. Starting as hand-drawn diagrams and evolving into automated software, the critical path method has become an essential part of planning a project.
