Question 8 A work system has five stations that have process
Question 8
A work system has five stations that have process times of 5, 9, 4, 9, and 8. What is the bottleneck time?
4
9
18
35
4 points
Question 9
Fabricators, Inc. wants to increase capacity by adding a new machine. The fixed costs for machine A are $90,000, and its variable cost is $15 per unit. The revenue is $21 per unit. What is the break-even point for machine A?
$90,000
90,000 units
$15,000 dollars
15,000 units
| 4 | ||
| 9 | ||
| 18 | ||
| 35 |
Solution
9. break even poing= fixed cost/ selling price - variable cost of the unit
fixed cost= $90,000, selling price= $21, variable cost = $15
= 90,000/21-15= 90,000/6= 15000 units
8. usually bottleneck is the longest activity duration time, so in this problem the bottleneck value is 9. option B is correct
