Yancey Productions is a film studio that uses a joborder cos

Yancey Productions is a film studio that uses a job-order costing system. The company’s direct materials consist of items such as costumes and props. Its direct labor includes each film’s actors, directors, and extras. The company’s overhead costs include items such as utilities, depreciation of equipment, senior management salaries, and wages of maintenance workers. Yancey applies its overhead cost to films based on direct labor-dollars.

At the beginning of the year, Yancey made the following estimates:

Required:

1. Compute the predetermined overhead rate.

2. During the year, Yancey produced a film titled You Can Say That Again that incurred the following costs:

Compute the total job cost for this particular film.

Complete the question by entering your answers in the tabs given below.

Required 1

Compute the predetermined overhead rate. (Round your answer to 2 decimal places.)

Complete the question by entering your answers in the tabs given below.

Required 1

Required 2

Compute the predetermined overhead rate. (Round your answer to 2 decimal places.)

Complete the question by entering your answers in the tabs given below.

Required 1

Required 2

Compute the total job cost for this particular film. (Round your intermediate calculations to 2 decimal places.)

Direct labor-dollars to support all productions $ 8,390,000
Fixed overhead cost $ 5,034,000
Variable overhead cost per direct labor-dollar $ 0.19

Solution

Answer to Requirement 1.

Predetermined Overhead Rate = Estimated Manufacturing overhead / Estimated DL Dollar
Estimated Manufacturing overhead = Fixed Manufacturing Overhead + Variable Manufacturing Overhead
Estimated Manufacturing overhead = $5,034,000 + (8,390,000 * $0.19)
Estimated Manufacturing overhead = $5,034,000 + $1,594,100
Estimated Manufacturing overhead = $6,628,100

Predetermined Overhead Rate = 6,628,100 / 8,390,000
Predetermined Overhead Rate = $0.79 per DL $

Answer to Requirement 2.

Total Job Cost = Direct Materials + Direct Labor + Overhead applied
Overhead applied = $0.79 * 2,517,000
Overhead applied = $1,988,430

Total Job Cost = $1,446,000 + $2,517,000 + $1,988,430
Total Job Cost = $5,951,430